Home Database Case studies Adapting overhead lines in response to increasing temperatures in UK
Website experience degraded
The European Climate and Health Observatory is undergoing reconstruction until June 2024 to improve its performance. We apologise for any possible disturbance to the content and functionality of the platform.
Case studies

Adapting overhead lines in response to increasing temperatures in UK

Adapting overhead lines in response to increasing temperatures in UK

Several energy transmission and distribution companies in the UK have begun to take the impact of increasing temperatures into consideration for the long-design of electricity distribution infrastructure. Rising temperatures can impact power lines by reducing their thermal rating (i.e. the maximum current allowed at a given temperature) and causing lines to sag to dangerous levels. By increasing the rated design temperature standard of overhead lines to accommodate projected temperature rises, transmission system operators can adapt to the increasing ambient temperatures experienced and projected throughout Europe.

 

Case Study Description

Challenges

The frequency of extreme heatwaves in the UK is expected to increase in the future. The UK Climate Projections 2009 project that summer temperatures will increase by up to 4°C in parts of the UK under a medium emissions scenario by 2080. Such ambient temperature increases pose a threat to transmission and distribution operators due to the thermal expansion of power lines when they are heated. Such thermal expansion can cause lines to sag, meaning their clearance from land can become a danger to the general public. Sagging may also result in contact with trees and other structures, which could result in electrocution or fires. Most European countries, including the UK, have legislation in place to maintain a minimum distance between power lines and the ground or structures, in order to ensure that potential instances of electrocution or fires are avoided. Higher ambient temperatures means that the electrical current that passes through overhead power lines must be reduced to prevent the overheating of equipment.

Furthermore, warmer power lines can result in decreased efficiency due to a process known as de-rating. UK power utilities have assessed that increasing temperatures under climate change could cause carrying capacity to decrease by 4-9% by the mid-21st century. All of these impacts ultimately result in risks of accidents, power cuts and revenue losses, as well as cascading network failures. These impacts are compounded by increasing electricity demand during heat episodes, for example due to air conditioning.

Objectives

UK transmission and distribution networks have set out to review and update overhead line ratings throughout their whole network. This entails establishing the operational maximum temperature which overhead lines may be subjected under climate change scenarios, and determining a design standard to accommodate the projected increases in line sagging. These adaptation measures increase energy security and reduce risks of electrocution and fire.

Solutions

Western Power Distribution (WPD) are delivering electricity to 8 million customers throughout a 55,500 km2 service area in the UK. WPD have benefited from a study led by the UK Met Office (the national weather service). The study ‘Energy Project 2 Climate Change Impacts on the U.K. Energy Industry Project’ utilised energy-sector expertise to identify climate change impacts on energy generation, distribution, transmission and demand. WPD cooperated with the Energy Network Association (ENA) (a trade body organisation funded by transmission and distribution licence holders) in order to operationalise adaptation measures based on the study and to make plans to combat power line de-rating.

Adaptation measures identified included increasing the height of poles supporting power lines, installing conductors with hotter operating limits or implementing the use of ‘low-sag’ conductors. WPD assessed that the increased exposure to higher temperatures under projected climate changes would result in a reduced allowable current with their current design standards of wood poles. This would result in efficiency losses, and potentially economic losses, for the operator. The most cost-effective measure identified was to increase the minimum design temperature of new overhead line routes, the achievement of which would typically increase the design height of wood poles by 0.5 metres. This increased height could accommodate the projected increases in sagging without exceeding legal limits on the height of overhead lines. Furthermore, WPD have, in partnership with other UK DNOs, recently completed a project to update the UK Distribution Industry’s understanding of conductor ratings for overhead lines. Through their cooperation with ENA, WPD will be implementing the findings as an update to national standards.

As part of this ongoing process, WPD and various other UK energy companies are also developing a software tool that will allow UK energy companies to optimise their overhead line ratings.

Relevance

Case developed and implemented as a Climate Change Adaptation Measure.

Additional Details

Stakeholder Participation

The process of identifying adaptation measures was coordinated through work with The Energy Network Association (ENA), with the designated Climate Change Adaptation Task Group facilitating discussions amongst government, regulating agencies and members of network operators. Through such stakeholder engagement, Western Power Distribution is pro-actively reviewing adaptation plans and subsequent measures.

Success and Limiting Factors

Detailed climate change impacts on the energy system were identified through a collaboration with multiple stakeholders in the context of the ‘EP2 Climate Change Impacts on the U.K. Energy Industry’ project (lead by the Met Office). Such collaborations with weather information services can enable rapid provision of data sets that are directly relevant for decision-makers in the energy sector. The identification of likely climate change impacts on the energy system in advance allows time to implement measures to increase the resilience of the system. In addition, through engaging with the ENA, members of electricity network operators are brought together on the ENA-led Climate Change Adaptation Task Group with government and regulating agencies. The Task Group produces approaches to identify impacts of climate change on electricity TSO and DSO networks, and develop measures to adapt to the impacts of climate change. Such exchanges of information can form an integral component of selecting cost-effective and efficient adaptation measures that can benefit both private actors and the public realms.

Costs and Benefits

The costs of procuring wooden overhead poles 0.5 meters taller depend on the height of the original pole, but they can be as little as around £10 (€11) per pole.

Under The Electricity Safety, Quality and Continuity Regulations 2002, overhead lines up to 33kV must not be at a height lower than 5.8 meters above the ground at the maximum likely temperature of the line.

Implementation Time

The implementation of new design standards is an ongoing, proactive process.

Life Time

The expected lifetime of wooden poles that support overhead lines is approximately 40-60 years. At the end of this asset lifespan, the poles could be replaced to comply with new design standards.

Reference Information

Contact

Paul Jewell
Western Power Distribution
E-mail: pjewell@westernpower.co.uk 

Reference

Western Power Distribution, Met Office and the Committee on Climate Change (UK) websites and documents

Published in Climate-ADAPT Feb 14 2019   -   Last Modified in Climate-ADAPT Apr 18 2024


Please contact us for any other enquiry on this Case Study or to share a new Case Study (email climate.adapt@eea.europa.eu)

Document Actions